Scope of Work

The scope of work for the projects was to remove the entirety of the failed sealant from two 12 story buildings and to replace all sealant with Dowsil CWS (Contractor’s Weatherproofing Sealant). Building #1 was completed in 2023 over a 5-month period and building #2 was completed over the same period in 2024. In addition to the sealant replacement, Dow DOWSIL™ Allguard Elastomeric Coating was applied to all pre cast concrete surfaces. Both buildings were inspected and approved by the project engineer following completion.

Project Details

Project: Caulking and Coating Project

Location: 1140/1150 Parkwest Place, Mississauga ON

Contractor: Highrise Restoration

Year Completed: 2025